Christian Brothers College Junior Campus, Adelaide

Construction

Client: Christian Brothers College
Duration: 22 Months
Delivery: AS 4916-2002 Construction Management
Value: $11.2m

Construction of a performing arts centre, innovative rooftop playing field overlooking Adelaide's picturesque parklands, chapel, state of the art classrooms, and a $2m interactive library. Mossop’s involvement with trade procurement was critical in the cost effective delivery of the project. The project was originally designed with steel frames, however as the project was scheduled to start during the BER project period and structural steel companies had an extremely high workload, potentially resulting in higher project costs, Mossop suggested changing the structure to concrete and was able to procure the trade at a significantly lower cost culminating in project savings.