• Hunt & Hunt
    Completed In 12 weeks

    Client: Hunt & Hunt Lawyers

    Supervising Consultant: Hassell

    The design and construction of 2200 m² of new commercial office fitout consisting of 52 offices, 28 workstations 7 meeting rooms, 12 auxiliary rooms/areas, centralized staff breakout hub and associated spaces. Project included operable wall and associate structure, floor coverings and all systems and loose furniture.

     

  • Hindmarsh Building 1 - Mossop Construction + Interiors
    Completed in 17 months

    Client: Haddon Heights Pty Ltd

    Supervising Consultant: Hardy Milazzo

    Design and construction of an extension, alteration and interior fitout in a 2,620m² office building including the refurbishment of the State Heritage registered Brompton Methodist Church originally constructed in 1875. This refurbishment included the repairs to the ceilings and walls internally and stone work externally while providing an alternative entry to the Heritage building in sympathy with its original construction. Heritage ID No: 11805, including the construction of a 2 level, 84 space carparl for the building.

  • University of Adelaide Relocation Project
    Completed in 6 months

    Client: The University of Adelaide

    Supervising Consultant: Materne Pennino Hoare.

    Design and construction management of building upgrade works, fitout and relocation of departments.

  • University of Adelaide CTA Project
    Completed in 10 months

    Client: University of Adelaide

    Design Consultant: Hardy Milazzo

    The University of Adelaide’s Common Teaching Areas, (CTA), project consisted of the upgrade of 8 lecture theatres, including the complete refurbishment of all common areas. The actual cost for the project was $2.49m - a considerable saving on the original budget of $3.2m.

  • 45 Pirie Street
    Completed in 23 months

    Client: Colonial First State Global Asset Msanagement

    Supervising Consultant: Coffey Projects

    Mossop Construction + Interiors undertook the refurbishment of base building toilets over 13 levels; base building lift foyers upgrades over 17 levels, lift cart upgrade to all 6 lifts; upgrade of base building services and complete new refurbishment of the ground floor foyer entrance, back of house and plaza forecourt at 45 Pirie Street. Works were completed in 38 stages over 18 levels of the building whiles the building tenants remained in full occupation.

Found 5 Results, displaying 1 to 5